Airport "Borispol" in Kyiv: The reconstruction of Terminal "B".

For today the work on reconstruction of terminal "B" of airport "Borispol" are executed. The press-service of the Ministry of transport and communication of Ukraine informs about this "QualityKievApartments"

«In the course of reconstruction it is mastered 89,88 million UAH. From the planned 94,98 million UAH.», – they speak in the department.

In the Ministry also have noticed that «terminal" D "building is executed on 23 %. For the specified amount of works have spent 927,32 million UAH. from planned 1661млн. UAH.».